Supplied and installed a frost protection trace heating system to over 250m of external stainless steel pipework up to 150mm dia. We also supplied a small amount of self regulating heating tape for installation by others to valves at the top of the BCV vessel.
Showing posts with label Frost Protection. Show all posts
Showing posts with label Frost Protection. Show all posts
Thursday, 18 December 2014
Thursday, 11 December 2014
University College London, Howland Street
For this new research centre at UCL, to be known as the Sainsbury Wellcome Centre, ESH supplied and installed trace heating to provide frost protection to the following external pipework:


- Ground floor - feed pipework to salt saturators
- Level 4 - Heat rejection pipework to cooler
- Level 6 - CHW and LTHW pipework
- Level 6 - Cold water pipework to pressurisation unit and bib taps
- Level 6 - Heat recovery pipework
550m of FBTBOJ self regulating heating cable was supplied and installed on all cold and chilled water pipework, along with 970m of H2OWAT55 for all other services.
Monday, 8 December 2014
New Primark Store, Northampton
ESH were contracted to supply and install a frost protection trace heating system to the external chilled water pipework on the roof, mezzanine area and service yard. The system was designed using type VCBOJ constant wattage heating tape.
Friday, 5 December 2014
Innovation House, Oxford
Within this brand new student accommodation building, ESH supplied and installed frost protection trace heating to two runs of external water pipework. Tapes were pre-terminated into JBT thermostats for quick installation on site.
LA Fitness Gym, Birmingham
Within this popular gym, ESH supplied and installed a simple frost protection trace heating system to external heating pipework associated with an air handling unit.
Tuesday, 2 December 2014
Salford Royal Hospital
Supplied and installed type VCBOJ8/2 constant wattage trace heating tape to provide frost protection to external chilled water pipework. The heating tape was straight traced underneath the pipework and temperature controlled using our type STCI thermostats.
Friday, 28 November 2014
Frankley WTW
Seven Trent Water's Frankley Water Treatment Works at Frankley, Birmingham, supplies drinking water to Birmingham and the surrounding areas. Part of the £31.5m project to upgrade Frankley WTW, ESH supplied and installed a total of 1270m of trace heating cable to perform the following duties:
- Provide frost protection to the water / lime pipework
- Temperature maintain the sodium bisulphite pipework at +15°C in a minimum ambient temperature of -20°C
Our FBTBOJ10/2 heating tapes were installed to the underside of the pipework in a straight trace configuration and secured to the plastic pipe using type FTA fixing tape.
Wednesday, 26 November 2014
Stockport WWTW
Monday, 17 November 2014
Lees Brook Community School, Derby
Thursday, 23 October 2014
Skanska, Doncaster
Supplied and installed a trace heating system to frost protect the cold water service pipework. Our Type ESTSBOJ10/2 self regulating heating tape was installed to the underside of the pipework in a straight trace configuration.
Tuesday, 14 October 2014
New Marks & Spencer Store, Stoke On Trent
ESH Trace Heating Ltd supplied and installed a frost protection heating system to the MWS, BCWS, HWS and LTHW pipework. Within this brand new retail outlet, over 200 metres of type VCBOJ constant wattage heating tape was required.
Monday, 13 October 2014
Light Microscopy Facility, University of Sheffield
Here at this new microscopy core facility for the School of Medicine and Biomedical Sciences, ESH designed, supplied and installed a trace heating circuit to provide frost protection to a short run of chilled water pipework.
Friday, 19 September 2014
Wednesday, 17 September 2014
Lightshaw WWTW
Designed, supplied and installed a trace heating system to provide frost protection to external plastic pipework.
Thursday, 4 September 2014
Veolia Environmental Ltd, Birmingham
Supplied and installed trace heating materials to repair an existing frost protection system.
Wednesday, 27 August 2014
Sudbury Health Centre
Thursday, 21 August 2014
Eastern Promenade, Barry Island
Part of the Welsh Governments renovation of the eastern promenade, ESH were contracted to supply and install a frost protection trace heating system to the internal copper pipework within the new promenade buildings.
Friday, 15 August 2014
St Ambrose Barlow RC High School, Manchester
Part of the Building Schools for the Future programme (BSF), this 1000 pupil high school and college required some trace heating work completed before it re-opens its doors in September. ESH were contracted to supply and install two trace heating systems to perform the following duties:
- Provide frost protection to the schools BCWS pipework
- Temperature maintenance of the DHWS flow and return pipework at +55°C
Monday, 11 August 2014
Radcliffe Observatory Quarter, Oxford

Oxford University's £70m Mathematical Institute is just one part of this £200m redevelopment of the 10-acre site.
ESH were contracted to design, supply and install a frost protection trace heating system to the external CWM pipework. Type FBT self limiting heating cable was used throughout this project.
Thursday, 7 August 2014
Salford WWTW